NW Beaver Drive Overlay

Project Description
NW Beaver Drive – Merle Hay Road to NW 66th Avenue

HMA (Asphalt) mill and overlay project along NW Beaver Drive from Merle Hay Road to NW 66th Avenue. The project will include a recreational trail.

Project Information (Updated: 9/20/21)

๐‘ƒ๐‘Ÿ๐‘–๐‘ฃ๐‘Ž๐‘ก๐‘’ ๐‘ˆ๐‘ก๐‘–๐‘™๐‘–๐‘ก๐‘–๐‘’๐‘ 

  • Various utilities have above-ground infrastructure installed in conflict with the proposed grade and, in some instances, too close to the trail. HR Green will be notifying them of the need to adjust.

๐ถ๐‘–๐‘ก๐‘ฆ ๐‘ƒ๐‘Ÿ๐‘œ๐‘—๐‘’๐‘๐‘ก ๐ถ๐‘œ๐‘›๐‘ก๐‘Ÿ๐‘Ž๐‘๐‘ก๐‘œ๐‘Ÿ๐‘  

  • Grimes Asphalt – The final segment of roadway paving (Zone 5) is expected to begin in the coming week(s) following completion and surface restoration of Zones 1-3 (Merle Hay Road to Coburn Lane) as well as completion of underground work in Zone 5. This involves the asphalt milling, shoulder widening, and overlay from west of Trail Ridge Drive through NW 48th Court and the side road reconstruction of these intersections. 
  • All-Star Concrete – Zone 4 driveways and side road paving (NW 51st Street) are expected to be completed this week. The remaining trail paving in Zone 3 (west of Coburn Lane) and commencement of trail paving in Zone 4 is also expected to occur this week. The Zone 6 trail extension (NW 48th Ct. to River Bend Drive) is being prepared for paving to occur as crews are available while waiting on other contractors in Zones 3, 4, and 5.
  • OnTrack – The contractor is expected to complete Zone 5 underground work and remaining culvert/storm sewer adjustments throughout the project by the end of the week. The final sanitary sewer manhole adjustments and lining will remain outstanding pending final ditch grading and contractor providing manhole lining quotes.
  • Wenthold – The contractor is on-site focusing on Zone 3 and 4 final grading to facilitate final surface restoration and trail construction, as well as beginning Zone 5 removals in advance of roadway paving operations.

๐บ๐‘’๐‘›๐‘’๐‘Ÿ๐‘Ž๐‘™ ๐‘๐‘Ÿ๐‘œ๐‘—๐‘’๐‘๐‘ก ๐‘๐‘œ๐‘š๐‘š๐‘’๐‘›๐‘ก๐‘  

Work is being focused on final surface restoration and completion of Zones 1 through 3 by the end of the month to align with the close of the permanent seeding window. Final surface restoration has been mostly completed through Zone 2 (east of Forest Drive). It is scheduled to be completed through Zone 3 within the fall seeding window (end of September), weather permitting. 



NW Beaver Drive Overlay Detour Route

Public Communication
Click here (PDF) to view the letter sent to residents on Wednesday, June 2.
Click here (PDF) to view the presentation or a copy of the electronic meeting is shown below from Tuesday, Mar. 23.
Click here (PDF) to view the letter sent to the property owners near the construction regarding the meeting.

NWBeaverOverlayClosure

Estimated Cost
$3,100,000

Contractor
Grimes Asphalt & Paving Corporation

Estimated Project Timeline
Utility Relocation & Construction Spring 2021

Engineer Design
Cory Shannon, Project Engineer
515.657.5308
cshannon@hrgreen.com

City Staff Project Contact
Matt Greiner, Public Works Director
515.278.0822
Email Matt Greiner

Communication to Residents

  • Tree clearing for construction letter sent Feb. 22, 2021 (PDF)
  • The second public information meeting was held on May 21, 2019, for this project. Click here to view the presentation from the meeting. 
  • On December 12, 2018, a public open house was held to discuss the improvements to NW Beaver Drive. Click here (PDF) to view the presentation given by HR Green at the public meeting.