NW Beaver Drive Overlay

Project Description
NW Beaver Drive – Merle Hay Road to NW 66th Avenue

HMA (Asphalt) mill and overlay project along NW Beaver Drive from Merle Hay Road to NW 66th Avenue. The project will include a recreational trail.

Project Information (Updated: 9/7/21)

๐‘ƒ๐‘Ÿ๐‘–๐‘ฃ๐‘Ž๐‘ก๐‘’ ๐‘ˆ๐‘ก๐‘–๐‘™๐‘–๐‘ก๐‘–๐‘’๐‘ 

  • CenturyLink – The conflict with on-grade splices has been addressed. The contractor can now proceed with a demo of these and continue with ditch grading. 
  • ICN – The hand hole conflict with the trail identified near Coburn will be relocated. The hand hole conflict at Trail Ridge has been confirmed and can be removed by the contractor/ICN. Similarly, the exposed conduit west of Coburn is abandoned and can be removed while grading. 

๐ถ๐‘–๐‘ก๐‘ฆ ๐‘ƒ๐‘Ÿ๐‘œ๐‘—๐‘’๐‘๐‘ก ๐ถ๐‘œ๐‘›๐‘ก๐‘Ÿ๐‘Ž๐‘๐‘ก๐‘œ๐‘Ÿ๐‘  

  • Grimes Asphalt – Waiting for substantial completion of Zones 1-3 (possibly 4) before authorized for next area of paving (Zone 5 thru the end of the project). 
  • All-Star Concrete – The trail crossing at NW 70th Avenue and NW Beaver Drive and a portion of Zone 4 driveways were completed this past weekend. The focus will now be on the remaining trail and driveways (and replacement) in Zones 1-3. While also continuing on Zone 4 driveways. Trail work in Zone 4 will follow. Zone 6 trail extension can be prepared at any time. Paving of NW 51st Street is tentatively scheduled for next Wednesday, Sept. 8.
  • OnTrack – The contractor was back on-site this week and began working on Zone 5 underground work. The focus has turned to address issues on prior zones to facilitate final grading in the coming week(s). Once this work is complete, the focus will shift back to Zone 5 storm sewer, driveway culverts, sanitary sewer service extensions, and hydrant relocations – one of which is tentatively scheduled to be done on Wednesday, Sept. 8. 
  • Wenthold – The contractor is on-site focusing on Zone 2 and 3 final grading in advance of final surface restoration, which is scheduled to occur in at least Zones 1 through 3 within the fall seeding window (end of September). 

๐บ๐‘’๐‘›๐‘’๐‘Ÿ๐‘Ž๐‘™ ๐‘๐‘Ÿ๐‘œ๐‘—๐‘’๐‘๐‘ก ๐‘๐‘œ๐‘š๐‘š๐‘’๐‘›๐‘ก๐‘  
Work is focused on final surface restoration and completion of Zones 1 through 3 in the coming weeks. 


NW Beaver Drive Overlay Detour Route

Public Communication
Click here (PDF) to view the letter sent to residents on Wednesday, June 2.
Click here (PDF) to view the presentation or a copy of the electronic meeting is shown below from Tuesday, Mar. 23.
Click here (PDF) to view the letter sent to the property owners near the construction regarding the meeting.

NWBeaverOverlayClosure

Estimated Cost
$3,100,000

Contractor
Grimes Asphalt & Paving Corporation

Estimated Project Timeline
Utility Relocation & Construction Spring 2021

Engineer Design
Cory Shannon, Project Engineer
515.657.5308
cshannon@hrgreen.com

City Staff Project Contact
Matt Greiner, Public Works Director
515.278.0822
Email Matt Greiner

Communication to Residents

  • Tree clearing for construction letter sent Feb. 22, 2021 (PDF)
  • The second public information meeting was held on May 21, 2019, for this project. Click here to view the presentation from the meeting. 
  • On December 12, 2018, a public open house was held to discuss the improvements to NW Beaver Drive. Click here (PDF) to view the presentation given by HR Green at the public meeting.