NW 70th Avenue Improvements

Phase III 

Project Update (as of 9/25/2020)
Punch list items are being completed by the contractor.  These items are due to be completed by fall 2020.

Project Update (as of 11/27/19)
In spring 2020, the sidewalk to the north side will be installed; grading will be done, permanent striping will be placed, and the area will be seeded. When the project starts-up in the spring, there will be single-lane closures through the project area.  Construction activities expected to begin the week of March 23rd.